The next slice is chosen for what it proves, not for what is easiest to demo.
Delivery model
A project that cannot be described in documents is a project that cannot be handed over, audited or defended. These are the artefacts each stage produces, and who they are for.
01Discovery
Discovery is bounded and paid. It ends in a written scope, not a proposal designed to sound inevitable.
| Question | What we examine | What you get |
|---|---|---|
| What task? | The decision or transaction the system must support, and who performs it today. | One-sentence purpose, agreed in writing. |
| What exists? | Current tools, spreadsheets, exports, manual steps and the cost of each. | System inventory with owners. |
| What constrains? | Deadlines, contracts, data residency, integrations that cannot change. | Constraint list, marked fixed or negotiable. |
| What is assumed? | Everything we would otherwise quietly believe. | Assumption register — the most useful page. |
| What next? | Build, buy, configure, or stop. | Recommendation with the reasoning shown. |
02Model
The model is the expensive part to change. It is agreed as a document, with the awkward cases named, before an interface exists to argue about.
Open questions are listed with their owner and the date they must be answered. They are not hidden in a backlog comment.
03Build
Each increment ends in a preview environment with real-shaped data, a short written note on what changed, and a decision: continue, adjust, or stop.
Each cycle
The next slice is chosen for what it proves, not for what is easiest to demo.
Each cycle
Code, tests and migration in one branch; no unreviewed schema drift.
Each cycle
Watching the people who will use it, in the environment, not in a screenshot.
Each cycle
What changed, what was decided, what was deferred and why.
Each cycle
Continue, adjust or stop — a stop decision is documented like any other.
Cadence is agreed per engagement. This page deliberately publishes no week counts: they would be invented before your scope exists.
04Release
Real records move once. The checklist exists so that the day is boring.
| Before | During | After |
|---|---|---|
| Rehearsal | Migration runs against a production copy; counts reconciled. | Discrepancy report signed off by a named person. |
| Access | Roles switched, shared logins retired, sessions invalidated. | Access register dated and stored with the runbook. |
| Rollback | Written step, tested once in staging, with a time estimate. | Decision threshold: what would make us use it. |
| Monitoring | Alerts routed to a person, not a group inbox. | First-week review of errors and slow paths. |
05Handover
Projects stall on access and decisions far more often than on code. Naming both sides up front is the cheapest schedule protection available.
From you
From us
06Change
Change 01
A change request states what is different, why it appeared, what it displaces, and what it costs in time or money. Verbal changes are noted and then either written or dropped.
Change 02
New work is rarely free. If the deadline is fixed, the displacement is scope; if scope is fixed, the displacement is the date. Both are your call, made with the trade-off visible.
Change 03
If discovery shows a configuration of tools you already own will do, we will recommend that and document why. A short project that ends early is cheaper than a long one that should have.
Next step
Send the task, the systems it touches and the deadline you are working to. The first reply is a set of questions, not a quote.